Nigeria's crude oil and condensate production in December 2025, under review, was affected by planned Maintenance work at Stardeep-Agbami Renaissance-Estuary Area (EA), and unplanned production facility outages.
The Nigerian crude oil and condensate average production in December 2025 stands at 1.54 mmbopd, depicting a slight decline amid 100% Upstream Pipeline Availability for its evacuation to export terminals.
The 40-inch 614 km Ajaokuta-Kaduna-Kano (AKK) Gas Pipeline being constructed by Oilserv Limited is at 91% completion. AKK Mainline has been completed, while the mainline welding works are as scheduled. Efforts are being intensified to complete the Intermediate Pigging Stations (IPS) and Block Valve Stations (BVS)
The Obiafu-Obrikom-Oben (OB3) Gas Pipeline, also being constructed by Oilserv Limited, is at 96% completion status. OB3 River Niger Crossing is completed, and all early works have commenced the Pilot Hole drilling. According to NNPC Ltd, the project is on course to be completed as scheduled